Short answer: ISE 2027 runs 2–5 February 2027 at Fira Barcelona Gran Via, with standard build-up on 26–31 January and a stand-height limit of 700 cm in most halls. Exhibition Stand Pro (VAV Grup) designs and builds AV-ready custom stands in its own production facility in İkitelli OSB, Istanbul and trucks them to Barcelona; send your hall, stand number and size on WhatsApp +90 532 457 67 78 or the quote form for a free first design and quote within 48 hours.
ISE 2027 at a glance
| Item | ISE 2027 (official event manual) |
|---|---|
| Dates | 2–5 February 2027 |
| Visitor hours | Tue–Thu 10:00–18:00, Fri 10:00–16:00 |
| Exhibitor access | 07:00–20:00 (Friday until 00:00) |
| Venue | Fira Barcelona Gran Via, Halls 1–8 (incl. 8.0 and 8.1), Congress Square, Upperwalkway |
| Organiser | Integrated Systems Events (AVIXA + CEDIA) |
| Design approval | Via Abraxys; standard deadline 30 Oct 2026 |
| Structural calculations | Due 17 Dec 2026 |
| 2026 edition | 92,176 unique attendees from 181 countries, 1,751 exhibitors, 101,000 m² |
Checked on iseurope.org and the ISE event manual on 30 October 2026.
Build-up and breakdown, day by day
| Phase | Date and time |
|---|---|
| Early build-up (on request) | 24–25 January 2027 |
| Standard build-up | 26–31 January 2027, 08:00–00:00 |
| Fine-tuning only, no freight | 1 February 2027, until 17:00 |
| Show days | 2–5 February 2027 |
| Show closes | Friday 5 February, 16:00 |
| Dismantling starts | Friday 5 February, 18:00 |
| Vehicles allowed back in | Saturday 6 February, 08:00 |
| Final dismantling deadline | 00:00, per the breakdown page of the event manual |
| Last CEVA / self-loader collections | Monday 8 February 2027, 18:00 |
Six standard build-up days are generous for most stands, but large LED walls, rigged truss and double-deck stands still need a slot plan. We plan deliveries by day so the heavy structure arrives first and screens arrive when the floor is finished.
Height and wall rules by area
| Area | Maximum stand height |
|---|---|
| Most halls | 700 cm |
| Hall 8.0 | 650 cm |
| Congress Square | 400 cm |
| Upperwalkway | 300 cm |
| Shell scheme | 245 cm |
Walls that face a neighbouring stand may not exceed 400 cm unless they are set back 100 cm from the boundary, and each side may be no more than 50% closed. Double-deck stands are allowed on space-only stands; an enclosed room under a deck needs smoke detection.
Why AV stands need a different build
ISE is the audiovisual and systems integration show, so stands carry more screens, projection and sound than at most fairs. That affects the build:
- Dark rooms and demo spaces need light-tight walls and ventilation, planned with the 50% closed-side rule.
- LED walls need load-bearing frames, cable routes and a power plan for Servifira’s electrical order.
- Acoustics matter when neighbours also demonstrate sound; soft finishes and closed meeting rooms help.
- Rigging goes through Servifira, so hanging banners and truss are drawn early.
Deadlines you cannot miss
- 30 October 2026: standard design approval (Abraxys). If your design is not yet submitted, contact the organiser’s approval team immediately.
- 17 December 2026: structural calculations.
- 9 January 2027: CEVA Showfreight orders for freight and lifting.
- Electricity orders go to Fira de Barcelona (Servifira) per the manual.
How a stand from Istanbul reaches Barcelona
Our stands are built and pre-assembled in İkitelli, then travel by truck through the EU customs union with Türkiye. Allow about one week of road transport; we fix the departure date against the first build-up day you are allowed. The stand arrives numbered, with assembly drawings, so build-up time goes into assembly, not fitting.
What to send for your free pre-design
- Hall and stand number, stand size and open sides
- Logo as a vector file and brand colours
- Screens, LED walls and demo equipment, with sizes, weights and power
- Number of meeting rooms or demo rooms
- Your Abraxys status: submitted, approved or not yet started
Get your ISE 2027 quote: request a quote or WhatsApp +90 532 457 67 78.
Related: ISE Barcelona exhibition page, MWC Barcelona 2027 floor plan and stand guide, exhibition stand builder in Spain and stand rules by venue 2026–27.
Official sources used
- https://www.iseurope.org
- https://eventmanual.iseurope.org/opening-hours/
- https://eventmanual.iseurope.org/build-up/
- https://eventmanual.iseurope.org/breakdown/
- https://eventmanual.iseurope.org/height-regulations-walls-pillars/
- https://eventmanual.iseurope.org/stand-design-approval/
- https://eventmanual.iseurope.org/deadlines-checklist/
- https://eventmanual.iseurope.org/electricity/
- https://eventmanual.iseurope.org/ceva-logistics-and-handling/
- https://www.iseurope.org/ise2026_facts_and_figures