Short answer: Exhibition Stand Pro (VAV Grup) designs and builds custom stands for Marble İzmir 2027, the International Natural Stone and Technologies Fair at Fuarizmir, 13–16 April 2027, in its own production facility in İkitelli OSB, Istanbul and delivers them to İzmir by road within Türkiye. Send your hall or plot number and stand size on WhatsApp +90 532 457 67 78 or through the quote form and you receive a free first design and a project-specific quote within 48 hours.
Marble İzmir 2027 at a glance
| Item | Marble İzmir 2027 |
|---|---|
| Dates | 13–16 April 2027 (Tuesday to Friday), the 32nd edition |
| Opening hours | 10:00–18:00 |
| Venue | Fuarizmir, Zafer Mah. 840. Sk. Fuar Alanı No:2, Gaziemir, İzmir |
| Organiser | İZFAŞ, hosted by İzmir Metropolitan Municipality; the site notes the fair is held under TOBB’s authorisation (Law No. 5174) |
| Scope | Natural stone and stone processing technology |
| Last edition (31st, 14–17 April 2026) | Nearly 1,000 exhibitors from 28 countries and 41 Turkish provinces; more than 150,000 m²; 50,983 professional visitors (4,010 foreign, 46,973 domestic) |
| Build-up and dismantling | Not published online; set in the organiser’s exhibitor documents |
| Official site | marble.izfas.com.tr |
Dates and figures were checked on the organiser’s official site and its 2026 news item on 29 October 2026.
The Istanbul to İzmir question
Most of our fairs are in the same city as our factory. İzmir is not, so here is how it works. The stand is made and pre-assembled in İkitelli, checked against your drawings, loaded and driven to Fuarizmir as a domestic delivery. No customs, no freight forwarder, no container. The crew that built it installs it.
The honest trade-off: a late change is harder to make in İzmir than at an Istanbul fair. So we freeze the design a little earlier than for Tüyap or İFM and keep any larger change in the workshop, where it can still be done before the trucks leave.
What a natural stone stand has to do
- Carry real weight. Slabs, tiles and sample walls are heavy. We size frames and plinths to the weights you send and spread the load across the floor.
- Show stone in the right light. Texture and veining are judged under light, so we plan neutral-white lighting and, where the layout allows, light that rakes across slab surfaces.
- Label every sample. Name, origin and finish (polished, honed, brushed) on each piece save your team from answering the same question all day.
- Handle slabs safely. Slab walls need forklift access and a clear route from the delivery point to the stand.
- Keep edges safe. Slab edges and corners at aisle height are a hazard, so we plan guards or rounded profiles wherever slabs lean or stand free.
- Offer a place to talk. Hosted buyers and trade visitors need a table. We put it out of the aisle.
Programmes that move buyers around the halls
The organiser’s site lists a D.esign Arena, a natural-stone design competition and a Hosted Buyer Programme, and its 2027 preparations also mention Marble Talks sessions, buyer delegations and B2B meetings. Programmes like these send visitors across the halls on a schedule. A stand that is easy to find, with a table ready for pre-arranged meetings, uses them best. Ask the organiser where the arena and the buyer meetings sit relative to your plot before you choose the stand’s orientation.
Venue: Fuarizmir, Gaziemir
The organiser’s fair-venue page lists four exhibition halls, 119,400 m² of open and enclosed exhibition space, a 15,600 m² foyer, four seminar rooms and parking for 2,500 vehicles on a 330,000 m² site. It does not publish individual hall sizes, floor loads or ceiling heights, so for heavy stone displays we ask the organiser for the data of your hall and fix the design only when we have it. Nor does it say which plots are indoors and which are in the open air; ask your contact.
Countdown to 13 April 2027
| Date | What happens |
|---|---|
| By Tue 22 Dec 2026 (16 weeks out) | You send plot number, size, logo, sample list and slab weights; we return a design direction and quote within 48 hours |
| Tue 19 Jan 2027 (12 weeks) | Design frozen; weights confirmed; handling needs noted |
| Tue 16 Feb (8 weeks) | Production in İkitelli: frame, plinths, slab wall, flooring, graphics |
| Tue 16 Mar (4 weeks) | Pre-assembly check, with real sample weights where possible |
| Tue 30 Mar (2 weeks) | Loading and trucking plan fixed |
| Tue 6 Apr (1 week) | Trucks scheduled to arrive on the first allowed build-up day, which comes from the organiser |
| Tue 13 Apr | Fair opens |
Why a stand built in Istanbul can still suit İzmir
- No customs and no international freight. Domestic road delivery is the whole transport plan.
- One team from factory floor to hall. The people who built the stand install it, which keeps drawings, parts and fitting in one hand.
- Finishing done before it travels. Painting, lacquer and graphics are finished in the factory, so the work on site is assembly.
What to send for your free pre-design
- Hall or plot number and the layout plan, with indoor or open-air noted
- Stand size in m² and open sides
- Logo as a vector file and brand colours
- Sample list: slab sizes, thicknesses, weights, finishes
- Number of staff and meeting seats
- The organiser’s exhibitor documents, once you have them
Get your Marble İzmir 2027 quote: request a quote or WhatsApp +90 532 457 67 78.
Türkçe sayfa: Marble İzmir 2027 stand firması. Related: exhibition stand builder in Türkiye, Expomed Eurasia 2027 stand builder (the same week, in Istanbul) and stand rules by venue 2026–27.
Official sources used
- https://marble.izfas.com.tr/en
- https://marble.izfas.com.tr/about-fair
- https://marble.izfas.com.tr/fair-vanue
- https://marble.izfas.com.tr/marble-izmir-exhibit
- https://stonenews.eu/71416/ (preparations for the 32nd edition)
- https://www.karar.com/sehir-haberleri/marble-izmiri-50-bini-askin-kisi-ziyaret-etti-2044082 (2026 results, Turkish press)