Bella Center Copenhagen Stand Builder Guide: Halls & Rules

•By Exhibition Stand Pro Team

Short answer: Bella Center Copenhagen offers around 65,000 m² of event space in five halls (A–E), with clear heights from about 3 m in Hall B to 12.5 m in Hall D. A double-deck stand needs Danish construction-authority approval via Bella Center, with drawings and certificates due 12 weeks before the event, and only Bella Center staff may rig from the ceiling. Exhibition Stand Pro (VAV Grup) designs and builds custom stands at its production facility in İkitelli OSB, Istanbul and installs them in Copenhagen; send your event, hall and stand number on WhatsApp +90 532 457 67 78 or the quote form.

Bella Center at a glance

Item Bella Center Copenhagen
Address Center Blvd. 5, 2300 Copenhagen S, Denmark
Event space Around 65,000 m² of flexible space, 5 halls (A, B, C, D – Bella Arena, E)
Hall sizes A 450–3,500 m² · B 12,500 m² · C 14,000 m² · D 675–7,000 m² · E 5,300 m²
Clear height to lighting A up to 8.90 m · B 3.0–3.35 m · C 4.30–6.85 m · D 11.7–12.5 m · E 9.30 m
Floor load (B, C, E) Point load 4,000 kg per 15 × 15 cm; twin-wheel axle 5,500 kg
Rigging capacity Per point: Hall A 500 kg, Hall C 200 kg, Hall E 500 kg per node; drop wires up to 99 kg
Loading areas Halls A, B2, B5, B6, C, D and E
Public transport Metro M1, Bella Center station, a few minutes’ walk from the main entrance
Airport About 10 minutes by car
Parking About 1,700 spaces on site (paid, APCOA)

Figures from Bella Center’s halls page, capacity chart and technical information sheet. Checked November 2026.

Hall heights: what fits where

The hall decides the design before anything else. Hall B, the largest single exhibition floor, has only 3.0–3.35 m to the lighting, so tall walls, brand towers and hanging banners do not work there. Hall C rises from 4.30 m (C1) to 6.85 m (C3 and C4); Hall E reaches 9.30 m and Hall D (Bella Arena) 11.7–12.5 m. Some zones are marked with a lower maximum build height on the event floor plan, and red zones cannot be built on at all. Ask the organiser for the floor plan with your stand marked before the first sketch.

Hall Clear height Good fit for
A Up to 8.90 m Raised structures, hanging signs
B 3.0–3.35 m Low, open stands; no hanging structures
C 4.30–6.85 m Standard custom stands; taller elements in C3/C4
D (Bella Arena) 11.7–12.5 m Double-deck stands, large rigged signs
E 9.30 m Double-deck stands, rigged signs

Stand rules that shape the design

From Bella Center’s exhibitor terms (September 2026 edition):

  • Double-deck stands: a two-storey stand without certification, or a podium over 1 m, needs construction-authority approval via Bella Center. Drawings, photos, material and fire certificates are due 12 weeks before the event. At least one 1.3 m stair exit; at most 49 people upstairs.
  • Rigging: only Bella Center staff fix wires and mount Bella Center walls, fascia boards and spots. You may hang your own chain block from the rigging point Bella Center sets. Two wires minimum per banner or sign.
  • Fire safety: decoration material class B; carpets class G (DS 1063.2), Dfl-s1 or NT Fire 007; furniture at least D-s2,d2. A firm stand ceiling over 9 m² needs extra sprinklers. Fire hose reels and cabinets must stay uncovered. Dispensations are requested 8 weeks before the event.
  • Power and services: ordered through the Bella Center webshop, usually by 4 weeks before the event; orders become binding 28 days before. Power runs 24 hours a day from the first build-up day until 12:00 the day after closing.

Your own event’s exhibitor manual takes precedence. Organisers often set earlier deadlines than the venue.

Upcoming events at Bella Center (2027)

Event Sector Dates (2027) Organiser site
WindEurope Annual Event Wind energy, 500+ exhibitors 20–22 April windeurope.org
Euroanaesthesia Anaesthesiology, 130+ exhibitors 29–31 May euroanaesthesia.org
UEG Week Gastroenterology 16–19 October ueg.eu

Dates as published by the organisers. For a double-deck stand at WindEurope 2027, the 12-week drawing deadline falls in late January 2027, so design work should start in December 2026.

Timeline for a custom stand at Bella Center

Weeks before opening Task
16–14 Brief, floor plan with stand location, first design
12 Double-deck or podium (>1 m) drawings and certificates to Bella Center
8 Fire-class dispensation requests, if any
6–4 Production and pre-assembly in Istanbul; services ordered in the webshop
2 Road freight to Copenhagen within the organiser’s delivery window
1–2 days Build-up in the organiser’s build-up window

How we deliver a stand to Copenhagen

  1. Brief and design: you send the event, hall, stand number, size and deadline. We reply with a first design and a project-specific quotation.
  2. Approval package: drawings, structural details, photos and fire certificates prepared for Bella Center and the organiser.
  3. Production: the stand is built and pre-assembled at our production facility in İkitelli OSB, Istanbul.
  4. Shipping: road freight to Denmark. Stand materials travel duty-free under the EU–Türkiye customs union with an A.TR certificate; exhibits you take back can go on an ATA Carnet.
  5. Build-up and dismantling: our crew installs the stand in the organiser’s window and works with the services Bella Center reserves for itself, such as rigging and power.
  6. After the show: reusable parts can be stored at our Düsseldorf warehouse for your next European show; we also have a local base in Hannover.

We are an independent stand contractor, not an official supplier of Bella Center or any organiser.

Sources

Frequently asked questions

There is no single venue-wide limit; Bella Center says it depends on the exact location of your stand. Clear heights to the lighting are up to 8.90 m in Hall A, 3.0–3.35 m in Hall B, 4.30–6.85 m in Hall C, 11.7–12.5 m in Hall D (Bella Arena) and 9.30 m in Hall E. Some zones carry a lower build-height limit on the event floor plan.
Yes, with approval. Under Bella Center's exhibitor terms, a two-storey stand without certification, or a podium higher than 1 m, needs approval from the Danish construction authorities via Bella Center. Drawings, photos, material and fire certificates are due 12 weeks before the event starts. The upper deck needs at least one 1.3 m stair exit and may hold at most 49 people.
Only Bella Center staff fix wires to the ceiling and mount Bella Center walls, fascia boards and spots. Bella Center establishes the rigging point; you may hang your own chain block from it. Banners and signs need at least two wires.
Bella Center's exhibitor terms require decoration material of class B, carpets of class G (DS 1063.2), Dfl-s1 or NT Fire 007, and furniture of at least D-s2,d2. A closed stand ceiling over 9 m² needs extra sprinklers; water-permeable coverings over 9 m² are allowed. Dispensation requests are due 8 weeks before the event.
Bella Center lists loading areas at Halls A, B2, B5, B6, C, D and E. Build-up times, vehicle access and unloading slots are set per event by the organiser, usually 1–2 days before opening. Crews can also use Metro line M1 to Bella Center station; the airport is about 10 minutes away by car.
Türkiye and the EU are in a customs union for industrial goods, so stand materials made in Istanbul travel duty-free with an A.TR movement certificate. Exhibits you take back home can go on an ATA Carnet; consumables cannot.

Stand Projenizi BaşlatınProject Brief

Fuar, şehir ve stand ölçüsünü paylaşın; proje kapsamını birlikte netleştirelim.

Proje bazlı teslimat
Kendi Üretimimiz
Talep üzerine portföy
Teknik destek

Global Fuar Stand Hizmet Bölgelerimiz

Dünyanın dört bir yanındaki fuar merkezlerinde anahtar teslim stand tasarım, üretim ve kurulum hizmetleri sunuyoruz. Hedef ülkenizdeki operasyonlarımız hakkında detaylı bilgi alın.

AraWhatsAppTeklif Al